Home News Corridor 5 selected as preferred corridor for the Mid North section of NTx South 
Map showing the original corridor options and Corridor 5. Corridor 5 runs south from Bundey, past Robertstown, between Eudunda and Kapunda, and continues towards Freeling. The original corridor options are shown for comparison.
14 October 2026

ElectraNet has selected Corridor 5 as the preferred corridor from Bundey to Freeling in NTx South, following detailed investigations and community engagement across the Mid North. 

Corridor 5 is the easternmost of the five Mid North corridor options considered for NTx South. It was selected after performing most strongly overall across the planning-level assessments and will now become the focus of future planning and investigation. 

Importantly, selecting a preferred corridor does not mean a route for the transmission line has been selected, or that NTx has been approved or will definitely proceed. 

Landholders within the corridor area are being contacted directly by ElectraNet. A corridor is a broad area for future investigations to identify an appropriate transmission line route. Selecting Corridor 5 allows us to focus future planning and investigations within the area we consider most suitable, based on the work completed to date. 

If NTx progresses, considerably more investigation, planning and engagement would be required before a potential transmission line route could be identified. 

Why was Corridor 5 selected for the Mid North? 

Corridor 5 was identified after communities participating in earlier engagement asked ElectraNet to investigate options further east of the original Mid North study area, particularly to reduce impacts on productive cropping land, homes and townships.  

Following this feedback, we expanded the study area and identified Corridor 5 as a potentially viable option. We then assessed all five corridors using the same assessment criteria and updated information to provide a consistent comparison.  

Overall, Corridor 5 performed most strongly across the planning-level assessments. In particular, it performed favourably in areas identified as important through community feedback, including potential impacts on more productive cropping land, homes and townships. Like every corridor considered, it also presents constraints and trade-offs that would require further investigation and management. 

Find out more about why Corridor 5 was selected: 

Thank you for your feedback 

Thank you to everyone who participated in our recent engagement on NTx South and shared their feedback, questions and local knowledge with us. 

This feedback has helped us better understand local conditions, concerns and priorities and has continued to inform our investigations and planning. The recent face-to-face engagement included sessions in Truro, Robertstown and Kapunda.  

Following consultation on the Draft What We Heard Report Volume 3, we have now finalised the report to include the additional feedback received. Read the final What We Heard Report Volume 3

A more detailed Response to Feedback document will be released in coming months, explaining how community feedback has been considered and used in our planning. We will also continue to release further fact sheets and project information as our work progresses. 

What happens next? 

With a preferred corridor now selected, our immediate focus will shift to finalising the Project Assessment Conclusions Report (PACR) as part of the Regulatory Investment Test for Transmission (RIT-T). 

The investigations undertaken on NTx to date have been important in developing a robust assessment of the project and informing the cost-benefit analysis that forms part of the RIT-T process. 

The PACR is currently expected to be released in late 2026 or early 2027. 

Selection of a preferred corridor does not represent a decision to proceed with NTx. The RIT-T process, including the regulatory assessment of the project and its costs and benefits, needs to be completed before ElectraNet determines when the project should proceed. 

As our immediate focus moves to completing the PACR, communities may see less on-ground investigation activity in Corridor 5 than might be expected following selection of a preferred corridor. Further detailed investigations and route development work will be undertaken as project planning progresses and greater certainty is established about the future timing of NTx. 

We will continue to keep landholders and communities informed as our work progresses. 