Home Responses to Community Information Session Questions

Responses to Community Information Session Questions

The following questions were taken on notice at our recent community information session and other events. 

ElectraNet plans, designs, operates and maintains transmission infrastructure in accordance with applicable safety standards and regulatory requirements.  

These standards and regulatory requirements would be applied to the design and assessment of any new asset including transmission lines.  

ElectraNet would only build assets where we can demonstrate they are in accordance with these requirements.  

ElectraNet’s approach to electric and magnetic fields (EMFs) is guided by scientific and medical research and relevant health guidance.  

ElectraNet continues to monitor EMF research and follows good electricity industry practice in the planning of new high-voltage assets.  

ElectraNet seeks to maximise the distance between transmission lines and homes wherever practicable, while balancing environmental, cultural heritage, agricultural and engineering considerations.  

Minimum safe separation distances are prescribed by Electricity (General) Regulations 2012 & AS/NZS 7000: 2016 Overhead Line Design standard. These standards would be used as the minimum setback requirements and ElectraNet will seek to achieve a much greater setback from houses than required where practicable. The final alignment would be developed through detailed investigations and consultation with affected landholders.  

As part of this ElectraNet would assess potential impacts such as noise, electric and magnetic fields (EMF), visual impacts and construction activities, and would consider design or alignment changes to avoid or reduce impacts where practicable.  

The line must comply with all applicable safety requirements, noise limits and EMF guidelines, regardless of its distance from a home.  

Point of clarification: During a recent Community Information Session, a 200-metre distance between homes and an indicative transmission line was discussed. This was one of several measures used to compare housing density and proximity across the five corridor options in the initial corridor comparisons setbacks of 400m, 1km and 2km were also used in this assessment. It was not a proposed or minimum separation distance between homes and a future transmission line. The location of any future transmission line would be determined through subsequent route development and design, if the project progresses.  

Detailed health and wellbeing assessments cannot be completed until the route and transmission line design have been further developed. Following selection of a preferred corridor and confirmation of project timing, health, safety and wellbeing considerations would be addressed through the project planning, design, and environmental assessment processes.

At this stage, relevant health, safety and wellbeing matters include potential noise, dust, and vibration impacts during construction, visual and amenity impacts, and noise and electric and magnetic fields (EMF) during operations.

More detailed assessment of these matters would be undertaken once the project design is further developed. The findings would inform route refinement, design, mitigation measures and the environmental impact assessment.

Detailed noise modelling cannot be completed until the route and transmission line design have been further developed. Following selection of a preferred corridor and confirmation of project timing, specialist noise assessments would be undertaken as part of the detailed design and environmental impact assessment under the under South Australia’s Planning, Development and Infrastructure Act 2016. 

Operational noise, including corona noise that may occur during wet or humid conditions, would need to comply with the applicable day- and night-time limits under South Australia’s Environment Protection (Commercial and Industrial Noise) Policy 2023.  

The assessment would consider noise at nearby homes, including the potential for sleep disturbance and would inform the final alignment and design. 

Construction noise would also need to comply with South Australian requirements, including the Local Nuisance and Litter Control Act 2016 and any conditions imposed through the project’s development approval.  

A construction noise management plan would set out the required controls, which may include work-hour restrictions, quieter equipment, advance notice to nearby landholders and processes for responding to complaints. 

Community members can access information on EMFs through recognised sources including the Australian Radiation Protection and Nuclear Safety Agency (ARPANSA) and the World Health Organisation. See a list of technical references information below: 

General links to information covering EMF 

Australian Radiation Protection and Nuclear Safety Agency –  https://www.arpansa.gov.au/understanding-radiation/radiation-sources/more-radiation-sources/electricity   

Extremely Low Frequency Fields, by World Health Organisation – https://www.who.int/publications/i/item/9789241572385    

Energy Networks Australia EMF handbook – energynetworks.com.au/resources/fact-sheets/emf-management-handbook/ 

ElectraNet has undertaken environmental constraints mapping, desktop studies and corridor assessments using available information on native vegetation, threatened species and ecological communities, protected areas, waterways and other biodiversity values. This information has been used to identify key constraints and inform the development and comparison of corridor options.

Following selection of a preferred corridor and confirmation of project timing, detailed ecological surveys would be undertaken to confirm the flora, fauna, habitats and biodiversity values present. The results would inform further route refinement and the project’s environmental impact assessment and approvals.

The project would seek to avoid environmental impacts wherever practicable, then minimise, mitigate and rehabilitate impacts that cannot be avoided, with offsets considered for residual impacts where applicable. This may include refining the alignment, adjusting the location of structures and access tracks, limiting vegetation clearance and applying specific construction controls.

Any remaining impacts would be assessed through the approvals process, including whether environmental offsets are required.

Available information on threatened species and their potential habitat, including the critically endangered pygmy blue-tongue lizard, has been considered through environmental constraints mapping and the corridor assessment process. 

Following selection of a preferred corridor and confirmation of project timing, targeted ecological surveys would be undertaken to confirm whether threatened species or suitable habitat are present.  

Survey results would be used to refine the route and locate structures, access tracks and other infrastructure away from threatened species and important habitat wherever practicable.  

Where impacts cannot be avoided, appropriate mitigation, management and, if required, offset measures would be developed through the required environmental impact assessment and project approval processes.

Following selection of a preferred corridor and confirmation of project timing, ElectraNet would assess potential impacts on birds through ecological surveys and specialist studies.  

This identifies important habitats, flight paths and higher-risk locations, such as areas near wetlands or where threatened species may occur. 

Where risks are identified, ElectraNet would first look at whether they can be avoided or reduced through the location and design of the transmission line.  

Other measures may include installing bird-flight diverters to make powerlines more visible and anti-roosting devices where birds roosting on structures could create a safety risk. 

The specific measures required would be determined through the environmental assessment and incorporated into the project’s design and management plans. ElectraNet would also monitor the effectiveness of these measures and make adjustments if required. 

bird-flight diverters to make powerlines more visible and anti-roosting devices where birds roosting on structures could create a safety risk. 

The specific measures required would be determined through the environmental assessment and incorporated into the project’s design and management plans. ElectraNet would also monitor the effectiveness of these measures and make adjustments if required.

Yes. Following selection of a preferred corridor and confirmation of project timing, ElectraNet would be required to undertake a detailed environmental impact assessment and geotechnical assessments. Geotechnical assessments allow us to understand the groundwater conditions. 

The environmental impact assessment would consider a range of environmental features within and near the corridor, including groundwater, watercourses, wetlands, native vegetation, threatened flora and fauna, threatened ecological communities, soils, habitats and protected areas. It would also assess potential impacts on Matters of National Environmental Significance, such as nationally listed threatened species and ecological communities. 

The assessment would identify where impacts can be avoided through further route and design refinement, as well as the measures required to minimise and manage any impacts that cannot be avoided during construction and operation. 

With a preferred corridor now selected for the Mid North section of NTx South (Bundey to Freeling), our immediate focus will shift to the cost-benefit analysis and finalising the Project Assessment Conclusions Report (PACR) as part of the Regulatory Investment Test for Transmission (RIT-T). 

The investigations undertaken on NTx to date have been important in developing a robust assessment of the project and informing the cost-benefit analysis that forms part of the RIT-T process. 

The PACR will set out the conclusions of this work and is currently expected for release in late 2026 or early 2027. 

With a preferred corridor now selected for the Mid North section of NTx South (Bundey to Freeling), our immediate focus will shift to the cost-benefit analysis and finalising the Project Assessment Conclusions Report (PACR) as part of the Regulatory Investment Test for Transmission (RIT-T). 

A preferred corridor is a broad area for future investigations as part of identifying an appropriate transmission line route. Selecting a corridor allows us to focus future route planning and investigations within the area we consider most suitable, based on the work completed to date. 

There is currently no confirmed timeframe for identifying or releasing the final route.  

A route would only be released after substantial investigations have confirmed that the route is feasible. These investigations would include on-ground environmental and cultural heritage surveys, engineering and geotechnical studies, and detailed discussions with affected landholders. 

The timing for future route development activities is under review, more information about project timing is expected to be available by early 2027. 

Community feedback is being considered alongside technical studies, environmental investigations, planning information and landholder discussion.  

Feedback has already influenced investigations, including expansion of the study area and assessment of Corridor 5.  

Following selection of a preferred corridor and confirmation of project timing, feedback from the community would continue to inform route development. As further opportunities for community input arise these will be communicated via our electronic mailing list and on the project website.  

NTx remains in the planning and assessment phase and has not been approved for construction.  

Project timing is under review and will continue to be informed by regulatory processes, demand forecasts and assessment outcomes.  

Further information is expected after completion of the Regulatory Investment Test for Transmission (RIT-T) process, which is expected by early 2027. 

No, the project remains in the planning and investigation stage, with no final route as yet determined. The selection of a preferred corridor for part of NTx South represents a narrowing of investigation areas and does not decide a final route.  

In addition, NTx is subject to the Regulated Investment Test for Transmission (RIT-T), which confirms project need, with environmental approvals and assessment also required under the Planning Development and Infrastructure Act 2016. 

No decision will be made to progress NTx to construction until all these investigations and approvals have been successfully completed. 

NTx South remains in the planning and assessment phase. No final route has been selected. 

ElectraNet is speaking with landholders, neighbours and communities to understand local issues, property use and potential impacts. 

If further investigations or studies are required on private land, ElectraNet would contact the landholder first and seek the landholder’s written consent through an access licence. We would discuss what work is proposed, when it may occur, access routes, biosecurity requirements and any property-specific concerns such as farming operations, livestock, gates, fences or other infrastructure. 

Where a transmission line passes through private land, an easement is required. An easement is a property right that allows the transmission line to be located, operated and maintained on that land.  

Importantly, the land remains owned by the landholder. 

ElectraNet’s preference is to reach agreement with landholders through direct discussion and negotiation. Landholders can ask questions, raise concerns and seek their own legal, valuation or other professional advice. 

The Land Acquisition Act 1969 (SA) and the Electricity Act 1996 (SA) provide the legislative framework for acquiring land rights for electricity infrastructure compulsorily where agreement cannot be reached.  

This is not ElectraNet’s preferred approach and would only be considered if required for the project and after reasonable efforts had been made to reach agreement. 

Compensation is assessed under the South Australian legislative framework including the Land Acquisition Act 1969 (SA), and established legal principles, it considers the circumstances of each property and the rights being acquired. 

If an easement is required, ElectraNet would work directly with affected landholders to reach agreement through discussion and negotiation. 

Compensation is not based on a standard payment per kilometre or per tower rate. It is assessed through a thorough valuation process undertaken by experienced independent property valuers using established valuation principles. This helps ensure compensation is assessed in a way that is just and fair. 

The valuation may consider factors such as: 

  • how the land is currently used 
  • the size and location of the proposed easement 
  • how the easement may affect the landholder’s ability to use and manage the land 
  • any reduction in productivity 
  • any reduction in property value. 


Landholders are encouraged to ask questions about the valuation approach, obtain their own independent valuation, and seek legal, financial or valuation advice. 
 

The compensation framework provides for reimbursement of landholders’ reasonable legal and valuation costs. 

Compensation is available where land rights, such as an easement, are required for the project. South Australia’s compensation framework does not provide compensation simply because a property is near a transmission line or has views of it. 

ElectraNet understands that nearby landholders and residents may still have questions about things like visual impacts, farming activities, access and construction works.  

These issues would be considered as the route is developed, through environmental and visual impact assessment and ongoing engagement with affected communities.  

Where ElectraNet’s activities cause a direct impact or loss, the situation would be assessed on a case-by-case basis.

ElectraNet understands that neighbouring landholders and nearby residents may be concerned about how a transmission line could affect property values, visual amenity and the long-term use and enjoyment of their properties.  

No final route has been selected for NTx South. Potential impacts on neighbouring properties would be considered as the project moves through route development, design and environmental assessment. This includes considering visual impacts, local land use, farming operations, access, construction impacts and community feedback.  

Neighbouring landholders can identify concerns such as views from their homes, access, farming operations or other ways they use their land.  

ElectraNet will continue to consider local concerns through the planning and assessment process and will look for opportunities to avoid, minimise or manage impacts where practicable. 

Compensation arrangements provided by ElectraNet include consideration of ongoing impacts, which are assessed and paid up-front as part of the compensation package. 

Under South Australia’s compensation arrangements, landholders receive a one-off payment when land rights, such as an easement, are required for a transmission project. Ongoing annual easement payments are not part of the current framework.  

A one-off payment means landholders receive the full amount upfront, rather than having to wait for payments over many years. This gives people flexibility in how they use the funds, whether that’s investing in their property, reducing debt, planning future works or meeting other needs. 

The compensation assessment is designed to reflect the long-term effect of the easement on the property. This may include how the easement affects the use of the land, farming activities and the property’s value. 

A single payment also provides certainty, as the compensation is agreed and paid upfront rather than depending on future arrangements or changes in property ownership. 

Separate compensation may apply if ElectraNet’s construction, operation or maintenance activities directly affect a property or landholder in a way that could not be originally foreseen and accounted for in the easement compensation process. This could include unforeseeable impacts to crops, fences, drainage, access tracks or other property improvements.  

Where such impacts are unavoidable, ElectraNet would work with the landholder to assess and address them in line with the applicable compensation arrangements.

No final route has been selected for NTx South. ElectraNet is continuing to assess route options and speak with landholders, neighbours and communities before any route is confirmed. 

If a landholder does not want the transmission line to cross their property, they should raise their concerns with ElectraNet as early as possible. This helps ElectraNet understand property-specific issues, such as land use, farming operations, access, infrastructure, biosecurity needs and other local constraints. 

ElectraNet would consider this information along with all other information available as part of route refinement, design and environmental assessment.  

Where practicable, ElectraNet would look for ways to avoid, minimise or manage impacts. This may include changes to the alignment, access arrangements, structure locations or construction methods. 

If an easement is required, ElectraNet’s preference is to reach agreement with landholders through discussion and negotiation. Landholders can ask questions, raise concerns and seek their own legal, valuation or other professional advice. 

Transmission infrastructure is essential public infrastructure. South Australian legislation provides a process for acquiring land rights where they are required and agreement cannot be reached. This is not ElectraNet’s preferred approach. It would only be considered if required for the project and after reasonable efforts have been made to reach agreement. 

Where an easement is acquired, compensation is assessed under the South Australian legislative framework and established legal principles. It considers the circumstances of each property and the rights being acquired.

ElectraNet will continue to engage openly and directly with affected landowners, near neighbours, local councils, stakeholders and the broader community throughout project planning and assessment. 

Engagement will include one-to-one meetings, letters, phone calls, community information sessions, online engagement and opportunities to provide feedback on project information and documents. 

Following selection of a preferred corridor and confirmation of project timing, ElectraNet will work directly with potentially affected landowners as part of the route development process, including on access, surveys, route planning, identifying potential impacts and compensation. 

Local knowledge and community feedback will continue to inform route refinement, impact assessment and project design. 

Compensation for easements is assessed under South Australian legislation, including the Land Acquisition Act 1969 (SA), and established legal principles.  

Each property is different. Compensation is assessed through a property-specific valuation process that considers the rights being acquired and how the easement may affect the use and value of the land.  

The Land Acquisition Act 1969 (SA) was reviewed through a Parliamentary Select Committee inquiry in 2017. Reforms following that review took effect in 2020. 

Those reforms were intended to improve how acquisition and compensation matters are managed. 

Further amendments were incorporated in 2021, relating to the timeframes between property acquisition and when the land can be used for the acquired use. 

ElectraNet must work within the compensation framework set by South Australian legislation. ElectraNet does not set or change that framework. 

Community members who would like to see changes to the compensation framework can raise those matters with their local Member of Parliament.

The effect of an easement on future land use would depend on the location, size and terms of the easement, as well as the circumstances of the property. 

An easement does not, by itself, stop land from being subdivided or developed. ElectraNet’s transmission lines already run through many growing areas in South Australia, including Mount Barker and Munno Para, and areas planned for growth such as Concordia and Gawler East. In these places, development has been planned around the transmission network. Where it is safe and suitable, transmission corridors can also form part of open-space areas, including walking trails, bike paths, dog parks and other community recreation links. 

If an easement is required, any impact on the use and value of the land would be considered by an independent valuer when compensation is assessed. 

The valuer must use recognised valuation principles. This includes considering the current lawful use of the land under planning laws, as well as any development potential that can be properly supported by evidence.  

If land is being rezoned, or if a future development proposal is well advanced, that may be considered as part of the valuation. However, compensation cannot be based on speculation. The assessment must be based on evidence, planning status and established legal principles. 

Landholders should tell ElectraNet about any known subdivision, rezoning or development plans as early as possible. This helps those matters be understood during route refinement, easement discussions and the compensation process. 

Any restrictions on land use within the easement would depend on the rights needed for the transmission line, including safety, access, operation and maintenance requirements. 

We are aware of the location of the Mt Rufus communications tower and have taken it into account in our corridor assessment. Other communications infrastructure would also be identified and considered as project planning progresses. 

As part of detailed design, we would assess whether the transmission line could interfere with communications infrastructure or signals, including through electrical interference, line-of-sight effects or proximity to existing equipment. Where an issue is identified, the design may be adjusted or other mitigation measures considered. 

Any direct impact on existing communications infrastructure would be addressed with the relevant asset owner, including any applicable compensation arrangements.

An easement would only be required where transmission infrastructure is located on private land. 

Transmission lines have existed alongside farming activities across South Australia for many years. In most cases, activities such as cropping and grazing can continue within an easement. 

Some activities may be restricted for safety reasons. For example, there are limits on buildings, tall structures and certain types of vegetation, excavation or activities that could affect safe clearances around the transmission line. 

Land next to an easement is not usually restricted simply because it is nearby. However, some activities close to the line may need to be considered if they could affect safety, access or maintenance. 

ElectraNet would discuss property-specific requirements with affected landholders as the project develops. The final easement agreement would set out any rights and restrictions that apply to the property. 

As part of the NTx Project Assessment Draft Report (PADR), ElectraNet considered and reported on a broad range of alternatives to NTx South, including: 

  • different transmission line routes and connection points 
  • different voltage and network configurations 
  • staged delivery options 
  • partial and full underground cable options 
  • submarine cable options 
  • high Voltage Direct Current (HVDC) technology options 
  • non-network solutions, including large-scale battery energy storage. 


ElectraNet has assessed five broad corridor options for NTx South (Bundey to Freeling), along with potential route variations within each corridor. The assessment has considered environmental, social, cultural heritage, land use, engineering, cost and constructability factors.
 

Corridor 5, which runs from Bundey to Freeling, was developed in response to consistent community feedback that ElectraNet should investigate an option further east, beyond Goyder’s Line to reduce impacts on high productivity agricultural land and homes. ElectraNet expanded the study area and applied the same constraints mapping, corridor development and multi-criteria assessment process used for the other corridor options. 

Based on the investigations completed to date, Corridor 5 provides the strongest overall balance across the factors assessed. 

However, no final route has been identified.  

Alternative technologies and broader network options are considered separately through the Regulatory Investment Test for Transmission (RIT-T) process. Further information on the options assessed and the basis for the proposed network solution is available in ElectraNet’s Project Assessment Draft Report (PADR) and will be reported in the upcoming Project Assessment Conclusions Report (PACR). 

Our assessment considers opportunities to follow existing infrastructure where practical, while balancing environmental, cultural heritage, engineering, safety, land-use, property, community and cost factors.  

The aim is to identify the best overall route rather than assume an existing corridor would always provide the lowest-impact option. 

Existing transport and infrastructure corridors have been considered and would continue to be investigated as the route is developed.  

However, it is not always practical or lower impact for a transmission line to follow them for its full length. 

Existing utility corridors can be constrained by other infrastructure and required safety clearances. Rail corridors are generally not wide enough to accommodate a transmission line and its required easement, while also maintaining the necessary safety clearances for rail infrastructure. 

They may also contain contaminated land associated with historic railway operations and often include tight curves and changes in direction that cannot be followed by a high-voltage transmission line. 

Highways and other established corridors may also pass close to homes, towns or environmentally sensitive areas, or require a longer and less direct route. 

NTx is being assessed through the Regulatory Investment Test for Transmission (RIT-T), which evaluates whether the preferred option provides the greatest overall benefit to electricity consumers. 

Forecast electricity demand, network needs and future generation scenarios form part of this assessment process. 

ElectraNet recognises the importance of agricultural land and food production to the region.  

In response to feedback from landholders during early project planning, ElectraNet has sought, where practicable, to identify a corridor that reduces interface with high-productivity agricultural land and farming operations. 

Following selection of a preferred corridor and confirmation of project timing, ElectraNet would work directly with affected landholders to understand their property, farming activities and future plans. This information would help inform route development, tower locations, access arrangements and construction timing to minimise disruption wherever practicable. 

In most cases, farming activities such as cropping and grazing can continue within a transmission line easement. Towers are typically spaced around 400 – 600 metres apart, allowing most of the land between them to remain in productive use. 

During construction, each tower site would require a temporary work area of approximately 50-by-50 metres. Once construction is complete, these areas would be rehabilitated, leaving a permanent tower footprint of up to 20-by-20 metres. 

ElectraNet already operates thousands of kilometres of transmission lines across South Australia, many of which coexist with agricultural land and food production. 

ElectraNet recognises that protecting farms and rural properties from weeds, pests and diseases is critically important. 

Biosecurity risks would be identified and managed before work begins and throughout the life of the project. This includes considering property-specific risks, on-ground survey, landholder requirements and seasonal conditions when planning access and work activities.  

ElectraNet’s Environmental Management System (accredited to ISO14001) and Safety and Sustainability Standards require environmental risks to be identified, controlled and monitored. 

ElectraNet employees, contractors and service providers would be required to follow biosecurity controls designed to prevent the introduction or spread of weeds, pests and diseases between properties. These controls may include the use of designated access routes, vehicle and equipment inspections, wash-down requirements and compliance with landholder biosecurity requirements.  

Where a property has specific biosecurity requirements, ElectraNet would work directly with the landholder to understand those requirements and incorporate them into access and work planning.  

ElectraNet would continue to monitor and manage biosecurity risks throughout construction and operation. Any concerns raised by landholders are investigated and addressed through ElectraNet’s environmental management and compliance processes.

Landholders would generally continue to manage their land as they do now, including routine weed control within the easement. 

ElectraNet is responsible for managing weed and biosecurity risks linked to its own activities. This includes access, field investigations, construction, maintenance and work around transmission structures. 

Before work occurs, ElectraNet would talk with landholders about property-specific requirements. This may include access routes, washdown needs, known weed areas, biosecurity controls and any other measures needed to protect the property. 

If ElectraNet’s activities cause or contribute to a weed issue, ElectraNet would work with the landholder to address it. Depending on the circumstances, this may include treatment, reinstatement, reimbursement of reasonable treatment costs, or engaging specialist weed, pest or disease-management services. 

Any material change to land management caused by the easement or transmission infrastructure may also be considered as part of the property-specific compensation assessment. 

ElectraNet has managed transmission lines in agricultural areas for over 25 years. Over this time there have been no known impacts on GPS/RTK systems from existing transmission lines through normal operations.  

Further technical investigations would form part of future project investigations and approvals processes.  

Transmission lines do not cause spray drift. Spray drift is caused by factors such as wind speed and direction, weather conditions, droplet size and the method of application. 

Agricultural chemical application can continue around transmission infrastructure. Ground-based spraying can generally continue as normal with some restrictions near and under the transmission line, provided appropriate electrical safety clearances are maintained.  

Aerial spraying can also continue, although pilots need to account for transmission lines and towers when planning and undertaking spraying operations as some restrictions apply. 

More broadly, normal farming activities such as cropping, grazing and harvesting can generally continue within and around transmission line easements. Transmission towers can be managed in much the same way as other fixed farm infrastructure, such as sheds, trees, water tanks and windmills. Their locations can be programmed into GPS and precision-farming systems so machinery can work around them. 

As the project is refined, ElectraNet will work with affected landholders to understand their specific existing farming practices and minimise impacts on normal agricultural operations wherever we can.

Detailed electrical and engineering investigations would be undertaken during design.  

Any required earthing measures would be undertaken by ElectraNet and form part of project design and construction.  

Such activities would be completed before a line is energised.

ElectraNet would discuss property access requirements and farming operations with affected landholders before any work occurs. This includes access routes, timing of works, biosecurity requirements, livestock, gates, fences, crops, irrigation, drainage and other property-specific issues. 

Where practicable, ElectraNet would seek to plan works in a way that avoids, minimises or manages disruption to farming operations. 

If ElectraNet’s activities cause loss or damage, claims would be assessed on their facts and in accordance with the applicable legal and compensation framework. This may include matters such as crop loss, damage to fences, gates, tracks, drainage or other infrastructure, loss of access, additional operating costs, or disruption to normal farming activities. 

ElectraNet would work with affected parties to seek a fair and reasonable resolution. Any agreed mitigation, reinstatement or compensation arrangements would depend on the circumstances of the property and the impact involved. 

ElectraNet would manage bushfire, electrical and public safety risks throughout the design, construction and operation of the transmission line. 

The line would be designed to meet all required electrical safety standards, including minimum clearances from the ground, buildings, vegetation and other infrastructure. Structures would include appropriate earthing and protection systems, and the line would be monitored, inspected and maintained throughout its operating life. 

Bushfire risk would be assessed as part of route development and detailed design. ElectraNet would manage vegetation within the easement where required, inspect assets for faults or damage and maintain access for inspections, maintenance and emergency response.  

ElectraNet would also work with the CFS, emergency services and landholders on access arrangements and fire management requirements. 

Public safety information would be provided to affected landholders and communities, including guidance on working, operating machinery and managing activities safely near the transmission line.  

ElectraNet must comply with its electricity licence conditions, relevant legislation and applicable safety and bushfire management requirements. 

ElectraNet designs, operates and maintains transmission infrastructure in accordance with various applicable Rules and Regulations, Australian/International Standards and ElectraNet Standards. This includes the maintenance and operation of the assets, once installed. 

Detailed project specific electrical studies are undertaken and verified independently to ensure the transmission line and substation infrastructure is fully compliant with internal and external clearances and insulation as required by these rules, regulations and standards. 

These measures ensure safe operation of the assets to minimise risks associated with arcing, flashover and induced electrical currents. 

NTx is being investigated to increase network capacity and respond to South Australia’s future electricity needs, including supporting economic growth and future demand.  

The need for NTx was identified well before extensive data centre demand was being factored into the electricity demand forecast.  

Data centres are one of several potential future electricity consumers considered within broader demand forecasts. ElectraNet does not determine whether third-party developments proceed or where they locate.  

NTx is being investigated to support South Australia’s future electricity needs rather than any specific third-party development. 

Increased transmission capacity is one factor that can support future electricity generation and industrial growth. However, ElectraNet does not determine whether independent third-party developments proceed or where they are located.  

Those projects make their own commercial decisions and are subject to their own planning and approval processes.  

There is currently no confirmed date for releasing more detailed route mapping. The immediate focus is on completing the Regulatory Investment Test for Transmission (RIT-T) process. 

Once the RIT-T outcome and broader project timing are known, ElectraNet will be better placed to confirm when detailed route investigations can begin.  

Developing a proposed route requires significant further environmental and cultural heritage surveys, engineering and geotechnical investigations, and discussions with affected landholders which will be undertaken alongside ongoing community engagement. 

Detailed route maps would be released once this work has progressed sufficiently to identify a credible proposed route within the preferred corridor.  

Any route shown at that stage would remain subject to further refinement and the required State and Commonwealth approvals. 

The corridor width varies depending on local conditions and the constraints identified in each area. At this stage, it is intentionally broad to provide enough flexibility to investigate different route options and avoid or minimise impacts. 

Following selection of a preferred corridor and confirmation of project timing, detailed environmental, cultural heritage, engineering and landholder investigations would be used, together with feedback received from the broader community to progressively develop a route within the corridor.  

As this work is completed, the area under consideration would narrow from a broad corridor to a proposed route and, eventually, a final transmission line alignment. 

The final easement would be much narrower than the corridor currently shown. 

Detailed design has not been completed because the preferred corridor and final route have not been confirmed and the project is still going through the Regulatory Investment Test for Transmission (RIT-T) process, which determines critical design elements.  

Based on current planning, the towers are expected to be approximately 50-to-75 metres high and generally spaced 400-to-600 metres apart. The exact height and spacing would vary depending on terrain, changes in direction, crossing requirements and the final engineering design. 

ElectraNet seeks to maximise the distance between transmission lines and homes wherever practicable, while balancing environmental, cultural heritage, agricultural and engineering considerations. 

Minimum safe separation distances from homes are prescribed by Electricity (General) Regulations 2012 & AS/NZS 7000: 2016 Overhead Line Design standard. These standards would be used as the minimum setback requirements and ElectraNet will seek to achieve a much greater setback from houses than required where practicable.  

Potential noise, electric and magnetic fields, visual impacts, safety requirements and construction impacts would be assessed as the route is developed. 

Tower locations and the alignment would also be discussed directly with affected landholders and adjusted where practicable to reduce impacts on homes and property operations.  

The final easement is currently expected to be approximately 60-to-80 metres wide, subject to detailed design. 

NTx is currently investigating one new high-capacity transmission line to be built in two sections:  

  • NTx South, which would run from the Mid North (Bundey substation near Robertstown) to Greater Adelaide. 
  • NTx North, which would run from the Mid North (Bundey substation near Robertstown) to Whyalla. 


The final infrastructure requirements remain subject to planning, engineering, environmental and regulatory assessment. 
 

Tower design would depend on factors such as terrain, engineering requirements, environmental constraints and safety clearances.  

Underground transmission at the voltages required for NTx is significantly more expensive and technically more complex than overhead transmission.  

Undergrounding is estimated to cost between 6-to-20 times more than overhead construction and may introduce additional land-use constraints relating to soil disturbance, drainage and agricultural practices.  

Under the Australian Energy Regulator’s (AER) regulatory framework, ElectraNet is required to identify the most prudent and efficient option that maximises benefits for energy consumers while minimising the risk of over-investment. 

The alternative of full undergrounding is considered cost-prohibitive as an alternative and would make the project economically unfeasible.  

Additionally, due to the length of the proposed connection, a different technical solution would be required, known as high-voltage direct current (HVDC) transmission, which would make this option even more expensive.  

Detailed engineering investigations would determine tower placement and infrastructure crossings.  

Safety, operational, environmental and engineering requirements would all be considered during route development and final design.  

Each crossing of roads, highways, other transmission and distribution infrastructure requires site specific design to ensure safe clearances are maintained throughout all potential environmental and network conditions that will be encountered during the life of the asset.

NTx South is intended to increase transmission capacity between the Mid North and Greater Adelaide so electricity can move from where it is generated to where it is needed across the network.  

The project is being investigated to support growing demand from homes, businesses and industry, while also enabling electricity generated across South Australia to be transferred more efficiently through the transmission system.  

NTx South is proposed to connect through Bundey Substation, which is a key connection point in South Australia’s transmission network and links it to the other states via an interconnector to NSW.  

This allows power to flow both into and out of Adelaide, improving network flexibility, supporting energy security and enabling transfers between generation sources, demand centres and existing network connections. 

The project would also strengthen the broader transmission network and work alongside other existing transmission infrastructure, including interconnector connections that form part of the National Electricity Market.

The project remains in planning and assessment, and the final design has not yet been determined. Current investigations of NTx South consider transmission infrastructure at 275kV, 330kV and 500kV, with solutions at 275kV or 330kV   considered to be the most likely outcome. The final configuration will be confirmed through the Regulatory Investment Test for Transmission (RIT-T) process.  

future network requirements are also being considered during planning, as required by the RIT-T, so that the infrastructure is appropriately sized for long-term needs. 

Any final design, including voltage, tower dimensions, easement requirements and safety clearances, would be confirmed before easement acquisition and discussed directly with affected landholders.  

Further engineering design would determine the technical parameters and configuration of the transmission line.  

The transmission line voltage would determine important parameters that affect line design, for example distances and heights of the towers and conductors. However, the distances required for 330 kV are similar to the ones for 275 kV. 

ElectraNet has over 25 years’ experience operating transmission lines across South Australia, with no impacts on GPS or RTK systems identified during that period through normal transmission line operations.  

Following selection of a preferred corridor and confirmation of project timing, detailed electrical, communications and engineering studies would be undertaken as part of project planning and design, to assess any potential interactions with GPS and RTK signals, communications infrastructure and other technologies.  

Existing communications assets, including telecommunications infrastructure, will also be considered during route development and impact assessment. 

NTx is being evaluated through the Regulatory Investment Test for Transmission (RIT-T) process, which considers future electricity demand, generation, augmentations, network constraints and long-term benefits for electricity consumers.  

This process includes simulating the electricity market for the next 25 years, taking future electricity generation and long-term utilisation into consideration.

Corridor 5 was identified after ElectraNet expanded the study area in response to consistent community feedback asking us to investigate an option further east, beyond Goyder’s Line. 

ElectraNet applied the same constraints mapping and multi-criteria assessment process used for the other corridor options. This considered environmental, social, cultural heritage, land use, engineering, cost and constructability factors. 

Corridor 5 provides the strongest overall balance across the factors assessed. It performs better in some areas and presents greater challenges in others, including its interaction with the Barossa Valley Character Preservation District.  

These trade-offs, along with community and landholder feedback, were considered before the preferred corridor was selected and announced. 

For more information see the Corridor 5 fact sheet here

Constraints mapping brings together available information about the land and identifies places where a transmission line may be more difficult, sensitive or unsuitable to locate. 

This includes information about homes, towns, agricultural land use, native vegetation, threatened species, waterways, cultural heritage, protected areas, existing infrastructure, future development areas, terrain and engineering requirements.  

Some constraints can be avoided, while others can be managed or require further investigation. 

Mapping these features allows ElectraNet to develop and compare corridor options on a consistent basis. It helps identify areas with fewer or more manageable impacts and provides a starting point for more detailed route investigations. 

For more information about how this was used for the identification and assessment of corridor 5 see the Corridor 5 Identification and Analysis Report, section 2.

ElectraNet recognises that different planning areas have different purposes and values. These have been taken into consideration throughout the process to date and will continue to be as the project progresses.  

The Barossa Valley Character Preservation District is focused on protecting the character of townships and the surrounding rural and landscape setting of the Barossa.  

The Roseworthy Future Growth Area has a different purpose. It is planned to support urban and industrial growth around Roseworthy. 

Both areas are important, and raise different planning considerations. 

For the Barossa Valley Character Preservation District, ElectraNet would consider landscape character, visual amenity, township character, agricultural land use and regional identity. 

ElectraNet would consider these areas and their requirements in the planning and design of the NTx Project, and would formally document considerations and outcomes as part of approvals processes, including the environmental impact assessment. 

While a preferred corridor though the Greater Adelaide portion of the project area has not been identified yet, ElectraNet is already working closely with State planning authorities as part of developing structure plans for Roseworthy Future Growth Area separately to our work on NTx.  

These plans help ensure growth is well planned and makes provision for the long-term infrastructure needs of the community. This planning work includes considering future urban and industrial development, planned infrastructure, land-use change, subdivision potential and how any transmission infrastructure can be coordinated with future growth.  

Should NTx affect this area, ElectraNet would continue its work with relevant planning authorities to inform route development and assessment, alongside environmental, engineering, agricultural, property and community factors.  

Visual impact assessment would be undertaken throughout route development and assessment. This would focus on important landscape values identified though the community engagement process.  

NTx is being investigated to increase capacity and security in South Australia’s high-voltage electricity network, meet growing demand, support economic growth, enable new electricity generation projects and strengthen transmission links for future industrial expansion.  

The Regulatory Investment Test for Transmission (RIT-T) assessment will determine whether the project represents the best overall outcome for electricity consumers.  

The need identified by the Australian Energy Market Operator (AEMO) for the Northern Transmission Project (NTx) is to increase the power system capability of the Mid North region of South Australia’s transmission network in order to: 

  • Support the expected increase in renewable generation north of Adelaide to meet growing electricity demand in Adelaide. 
  • Ensure adequate network capacity and supply for large industrial loads (LILs). 
  • Alleviate congestion restricting the transfer of renewable energy from the Mid North to the rest of the National Electricity Market (NEM). 

In line with this identified need, NTx South is being investigated to increase capacity in South Australia’s high-voltage transmission network so it can accommodate growing electricity demand and support future economic growth. 

Demand is expected to increase as households, industry, mining, steelmaking, defence-related development and other large electricity users require more power. 

NTx South would strengthen the network between the Mid North and Greater Adelaide, improve energy security by providing an alternative transmission pathway to Adelaide, and help relieve network constraints that can limit the efficient movement of electricity. 

The project is also designed to support the increasingly two-way nature of South Australia’s electricity system, where power flows both into and out of Adelaide depending on where generation and demand are located. 

If approved, the project would benefit electricity consumers by supporting a more efficient, secure and flexible network while helping connect future generation and major loads across the State. The project remains subject to the Regulatory Investment Test for Transmission (RIT-T), which will determine whether it represents the best overall outcome for electricity consumers. 

If approved, NTx would be funded as part of South Australia’s electricity transmission network. Like other transmission infrastructure, the cost would be recovered through network charges paid by electricity users over time. 

Before the project can proceed, it must complete the Regulatory Investment Test for Transmission (RIT-T), which is designed to determine whether it is the best-value solution for consumers. The Australian Energy Regulator (AER) would then independently assess the project’s costs and determine what costs can be recovered through network charges. 

Growth in demand from large industrial customers is expected to help spread network costs across more electricity users over time.  

The AER provides independent oversight to ensure only prudent and efficient project costs can be recovered. 

NTx is unlikely to have a material impact on overall electricity bills because transmission charges account for only a small proportion of total electricity costs.  

The Regulatory Investment Test for Transmission (RIT-T) process is specifically designed to assess whether the preferred option delivers the greatest overall benefit to electricity consumers.  

NTx remains in the planning and assessment phase, and project costs continue to be refined as investigations progress.  

The Project Assessment Draft Report (PADR) identified a draft preferred option for NTx South involving a new 275kV transmission line between Bundey and the Bolivar/Dry Creek area, with an estimated capital cost of approximately $1.4 billion with a net market benefit of between $356 – $640 million.  

This estimate is based on preliminary analysis and will change as we progress the required further planning, engineering design, environmental investigations and consultation.  

The project’s costs and benefits must be assessed through the Regulatory Investment Test for Transmission (RIT-T) process.  

NTx is intended to increase the capacity of South Australia’s transmission network so electricity can be moved more efficiently between areas of generation and areas of demand. This would help connect growing electricity generation around the state with homes, businesses and industry to support new large industrial loads, reduce network congestion and strengthen the transmission backbone.  

NTx South would also provide an additional transmission pathway into, and out of, Adelaide, improving energy security and resilience if parts of the existing network are affected by extreme weather or bushfire events.  

By increasing network capacity and improving the movement of electricity across the system, the project is intended to support future economic growth, new investment and employment opportunities while helping maintain a reliable and efficient electricity supply.

The South Australian transmission network is owned by the South Australian Government though the Transmission Lessor Corporation. ElectraNet has leased and operated the transmission network since 2000, under a 200-year lease. 

ElectraNet will seek to maximise opportunities for Australian steel, products and services wherever practical. 

Australian steel has been used for some elements of similar ElectraNet projects and NTx intends to continue that trend.   

However, the majority of the requirement for steel is for transmission towers where recent projects have used steel sourced internationally. The Australian steel industry has not been able to compete successfully for the provision of tower steel in recent years. 

As part of early project planning, ElectraNet has and continues to engage with Australian steel producers, fabricators and industry suppliers to better understand local capability and supply-chain capacity. 

As project planning progresses, ElectraNet will continue to explore opportunities for Australian industry participation. We will continue to engage with local industry and suppliers and work to develop a solution that will allow Australian sourced steel to compete with international suppliers and therefore potentially be used by this project.

ElectraNet is committed to realising benefits for local communities wherever practicable as part of their project delivery.  

These could include local procurement, employment or other community benefit initiatives.  

Identification of local opportunities would be undertaken in consultation with local communities.  

ElectraNet recognises that different planning areas have different purposes and values. These have been taken into consideration throughout the process to date and will continue to be as the project progresses.  

The Barossa Valley Character Preservation District is focused on protecting the character of townships and the surrounding rural and landscape setting of the Barossa.  

The Roseworthy Future Growth Area has a different purpose. It is planned to support urban and industrial growth around Roseworthy. 

Both areas are important, and raise different planning considerations. 

For the Barossa Valley Character Preservation District, ElectraNet would consider landscape character, visual amenity, township character, agricultural land use and regional identity. 

ElectraNet would consider these areas and their requirements in the planning and design of the NTx Project, and would formally document considerations and outcomes as part of approvals processes, including the environmental impact assessment. 

While a preferred corridor though the Greater Adelaide portion of the project area has not been identified yet, ElectraNet is already working closely with State planning authorities as part of developing structure plans for Roseworthy Future Growth Area separately to our work on NTx.  

These plans help ensure growth is well planned and makes provision for the long-term infrastructure needs of the community. This planning work includes considering future urban and industrial development, planned infrastructure, land-use change, subdivision potential and how any transmission infrastructure can be coordinated with future growth.  

Should NTx affect this area, ElectraNet would continue its work with relevant planning authorities to inform route development and assessment, alongside environmental, engineering, agricultural, property and community factors.  

Visual impact assessment would be undertaken throughout route development and assessment. This would focus on important landscape values identified though the community engagement process.  

ElectraNet integrated a visual assessment as part of the corridor assessment process. The visual assessment used modelling and analysis that considered topography and the location of dwellings, tourist assets, heritage places, character areas and townships.  

Further assessment of the potential impacts on tourism, visual amenity and regional character would be undertaken as part of further project analysis and route development.  

The assessment of project impacts on tourism, visual amenity and regional character will be formally reported as part of the environmental approval impact assessment.

Known heritage places (including Aboriginal and non-aboriginal heritage), culturally significant areas and local landmarks have been considered through constraints mapping and the corridor assessment process.

Following selection of a preferred corridor and confirmation of project timing, more detailed investigations would be undertaken within the preferred corridor. This would include reviews of heritage registers and other available records, field surveys, councils, landholders and local communities, and assessment of places identified through community engagement. Engagement with Traditional Owners to identify Aboriginal cultural heritage and cultural values within the corridor would also be undertaken.

Findings from these activities would be used to refine the route and locate towers, access tracks and other infrastructure away from important places wherever practicable.

Where impacts cannot be avoided, appropriate protection and management measures would be developed through the environmental impact assessment, cultural heritage processes, and detailed design and construction methodology development.

ElectraNet has undertaken some early visual assessment and modelling as part of the corridor evaluation process. This has considered matters such as topography, landscape character, viewing locations and proximity to homes. However, this work is preliminary and is intended to support comparison of the broad corridor options. 

We recognise that visual impact is one of the most significant concerns for communities and landholders.  

Following selection of a preferred corridor and confirmation of project timing, ElectraNet would undertake detailed visual modelling and landscape assessment as the route and infrastructure design are developed. 

This work would be undertaken with specialist visual and landscape experts, heritage consultants, landholders and local communities. It would consider views from homes, roads, towns, tourism and recreation locations, culturally important places and valued landscapes. 

The findings would be used to minimise visual impacts as much as practicable. This may include increasing separation from sensitive viewing locations, using terrain or existing vegetation to reduce visibility, adjusting tower locations and considering the placement and design of associated infrastructure.

ElectraNet will continue to engage openly and directly with affected landowners, near neighbours, local councils, stakeholders and the broader community throughout project planning and assessment. 

Engagement will include one-to-one meetings, letters, phone calls, community information sessions, online engagement and opportunities to provide feedback on project information and documents. 

Following selection of a preferred corridor and confirmation of project timing, ElectraNet will work directly with potentially affected landowners as part of the route development process, including on access, surveys, route planning, identifying potential impacts and compensation. 

Local knowledge and community feedback will continue to inform route refinement, impact assessment and project design. 

Community feedback is considered alongside technical studies, environmental investigations, planning information, landholder discussions and submissions received during formal consultation processes.  

Feedback has already influenced project investigations, including expansion of the study area and the identification and assessment of Corridor 5.  

Local knowledge and feedback would continue to inform future planning activities including route development and detailed design. As the project develops, we will continue to inform communities about opportunities to provide feedback and how their input has shaped decision-making.  

The best way for stakeholders to stay informed is by registering for regular project updates.  

We also welcome participation through community events, one-to-one discussions, consultation opportunities, feedback processes and project publications.  

ElectraNet has committed to ongoing engagement to ensure communities and landholders can continue providing information and feedback as planning progresses. 

ElectraNet believes trust is earned through transparency, accountability and consistently delivering on its commitments.  

As South Australia’s transmission network provider, ElectraNet has decades of experience planning, building and operating critical electricity infrastructure and working with landholders, communities and Traditional Owners.  

For NTx, we are committed to providing clear information, explaining how decisions are made, considering community feedback, and demonstrating how that feedback has informed project planning.  

While we may not always reach agreement with every stakeholder, we are committed to making evidence-based decisions, communicating openly about them and delivering the project responsibly and safely. 